62. An excavation will begin on April 15. What is the LATEST date that Underground Service Alert should be notified

Answer: C

Explanation:

The latest date that Underground Service Alert should be notified is April 13.

To ensure safety and proper planning for the excavation starting on April 15, the Underground Service Alert must be notified at least two working days prior. Therefore, the latest notification date would be April 13.

A) 01-Apr

Notifying Underground Service Alert on April 1 is too early, as it exceeds the required notice period. This option does not align with the timeline needed for the excavation scheduled for April 15.

B) 08-Apr

While notifying on April 8 meets the requirement of providing notice well in advance, it is not the latest date allowed. Therefore, this option is incorrect as it does not represent the maximum allowable notification date.

C) 13-Apr

This is the correct option because it is the last possible date to notify Underground Service Alert before the excavation begins on April 15. Given the requirement for two working days' notice, notifying on April 13 ensures compliance with the timeline.

D) 17-Apr

Notifying Underground Service Alert on April 17 is too late, as it falls after the excavation has already begun on April 15. This option does not satisfy the requirement for advance notice and is therefore incorrect.

Conclusion

The correct answer, April 13, is the latest possible date to notify Underground Service Alert, adhering to the requirement for a two-day notice before the excavation. Options A, B, and D either fall outside the needed timeframe or do not represent the latest date, confirming that C is definitively the right choice.