88. Client A's mechanic's lien is dated March 2nd and recorded March 5th. Johnson's Client B's lien is dated March 3rd and recorded March 4th. A tax lien and a separate judgment were filed on March 10th. Which of the following has priority?

Answer: D

Explanation:

The tax lien has priority.

In this scenario, the tax lien takes precedence because it is filed after the other liens but is given priority due to its nature as a government claim. Tax liens generally supersede mechanics liens and other types of liens regardless of their recording dates.

A) Client A's lien

Client A's mechanic's lien is dated March 2nd and recorded on March 5th. While it may seem to have an earlier date than Client B's lien, it does not have priority over tax liens, which are granted superior status by law.

B) Client B's lien

Client B's lien, dated March 3rd and recorded on March 4th, is subordinate to both Client A's lien and the tax lien. Although it is recorded before the tax lien, tax liens typically take precedence over mechanics liens.

C) the judgment

The judgment filed on March 10th occurs after both mechanics liens and does not have priority over the tax lien. Judgments usually follow the order of recording, but tax liens hold a higher priority status than judgments.

D) the tax lien

The tax lien, although recorded later than both mechanics liens, is superior due to its classification as a government claim. Tax liens are given priority by law over other types of liens, including mechanic's liens and judgments, which is why it prevails in this case.

Conclusion

The tax lien is definitively the correct answer due to its legal priority over all other types of liens listed. Client A's and Client B's liens, while recorded earlier, do not compare to the authority held by a tax lien, which is recognized as a superior claim by the legal system. Similarly, the judgment is also subordinate to the tax lien, confirming its priority status.