98. During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings. What should the project manager do?

Answer: B

Explanation:

Communicate directly with the director and inform them of the communications management plan

Addressing the situation effectively requires the project manager to communicate directly with their director to clarify the communications management plan. This step ensures that all changes are properly channeled through the project manager, thereby reducing confusion within the project team.

A) Discuss the issues with the project team and let them know that the project manager will handle scope changes

While discussing issues with the project team is important, it does not address the root cause of the problem, which is the direct communication between the director and the client. This option fails to resolve the miscommunication at the higher management level and may leave the project team feeling unsettled without a clear directive from their project manager.

B) Communicate directly with the director and inform them of the communications management plan

This is the most appropriate action as it directly addresses the issue of miscommunication. By informing the director of the communications management plan, the project manager can establish the proper channels for scope changes and ensure that all stakeholders are aligned, ultimately fostering a more cohesive project environment.

C) Review the stakeholder engagement plan and put in place any existing actions accordingly

Although reviewing the stakeholder engagement plan could be beneficial, it does not directly address the immediate issue at hand. This option may lead to further delays in resolving the communication breakdown, as it focuses on retrospective actions rather than proactive solutions.

D) Communicate directly with the client stating that any scope changes must go through the project manager

While this action might seem effective, it could lead to further complications by bypassing the director and potentially undermining their authority. It is crucial for the project manager to maintain a collaborative relationship with both the director and the client, making this option less suitable for the situation.

Conclusion

Option B is definitively the correct choice as it directly addresses the core issue of miscommunication and establishes the necessary framework for managing scope changes. The other options either do not resolve the miscommunication effectively or could exacerbate the existing confusion within the project team. Establishing clear communication channels is essential for project success and team cohesion.