22. During the daily project meeting, the project manager informs the project team that two additional software applications will be upgraded as part of the project. The manager then walks the team through the changes in the project plan and asks if anyone has any concerns.

Answer: B

Explanation:

Communicating the change

The project manager is actively informing the team about the upgrade of two additional software applications, which reflects the act of communicating the change clearly to the project team.

A) Identifying the change

While identifying a change is an important initial step in change management, the question context emphasizes the project manager's action of informing the team about the upgrade, which goes beyond merely identifying the change.

B) Communicating the change

This option is correct as it directly addresses the project manager's action of conveying information about the software application upgrades to the team. Effective communication is crucial to ensure that all team members are aware of the changes and can raise any concerns.

C) Evaluating the change

Evaluating the change involves assessing the implications and impacts of the change on the project. However, the project manager's role in this scenario is focused on communication rather than evaluation, making this option incorrect in the context provided.

D) Deciding if the change will be implemented

This option suggests a decision-making process regarding the implementation of the change. Since the project manager is already informing the team about changes that will occur, this indicates that the decision has been made, thus making this option incorrect.

Conclusion

The correct answer, "Communicating the change," highlights the necessity of keeping the project team informed about project updates. Other options either relate to preliminary steps or subsequent actions that are not relevant to the context of the project manager's communication during the meeting.