58. In this time study, which step will the bank manager take next?

Answer: B

Explanation:

Calculating the number of cycles to observe.

The next step the bank manager will take is calculating the number of cycles to observe, which is crucial for ensuring the accuracy and reliability of the time study.

A) Informing the worker who will do the job.

While informing the worker about their assigned tasks is important, it is not the immediate next step in the context of a time study. The manager must first determine how many cycles of the task need to be observed to gather sufficient data for analysis.

B) Calculating the number of cycles to observe.

This is the correct option as it directly relates to the planning phase of the time study. By calculating the number of cycles, the bank manager ensures that they will collect enough data to accurately assess the time it takes to complete the job, which is essential for the subsequent steps in the study.

C) Calculating the normal time.

Calculating the normal time is an important part of conducting a time study, but it typically occurs after determining how many cycles will be observed. The focus at this stage is on establishing the data collection parameters rather than analyzing the time itself.

D) Calculating the standard time.

Calculating the standard time is a later step that follows the determination of normal time. It incorporates allowances for rest and delays, but first, the number of cycles to observe must be established to ensure accurate data collection.

Conclusion

Calculating the number of cycles to observe is the foundational step that precedes further calculations in the time study process. This step ensures that the manager can gather adequate data for meaningful analysis, while the other options, although relevant, do not directly pertain to the immediate next action required in this context.